Today, on October 12, 2024, Acting Director Zoran Drobnjak with associates visited the works on the E-763 Highway construction project, Pakovraće-Požega section.
In addition to all the works on this construction site, from the works on drainage systems, asphalting, electro-mechanical equipment of the Laz tunnel, installation of elastic-retaining fence, it is necessary to highlight the works on the rehabilitation of the landslide that occurred in the middle of this year on the section of the construction site of this highway.
The landslide is located directly behind the Munjino brdo tunnel, in the direction of Požega, between two bridge structures with a length of about 300m.
The contractor is repairing this landslide by placing 109 piles at a depth of 35m on both sides of the highway under construction (49 piles on one side and 60 piles on the other).
Otherwise, the Contractor plans to break through the right pipe of the Munjino brdo tunnel soon, and the left pipe in the second half of December.