WORKS ON THE BRIDGE OVER THE TISA RIVER NEAR SENTA

The public enterprise “Roads of Serbia” continuously carries out activities on the regular maintenance and protection of state roads of the first and second category, including all associated road facilities - bridges, overpasses and other traffic structures throughout the Republic of Serbia.

Urgent works are underway on the bridge over the Tisa river near Senta, on state road of II A category number 105, which started due to the damages observed that required urgent intervention to preserve traffic safety.

So far, the following works have been carried out: protection of the steel structure from corrosion, rehabilitation of the reinforced concrete slab of the footpath and the diagonal of the main support, repairs of transverse and longitudinal supports, rehabilitation of parts of the pavement slab, installation of waterproofing, asphalting of the pavement on the bridge and on the access road, as well as the removal of traffic barriers or speed bump.

In the final phase of the works, the installation of 11 expansion joints is currently being carried out.

The expected completion of the works is around May 20, 2025, according to the weather condition.

 

With the completion of this intervention, the bridge will be technically correct and completely safe for traffic, which is the main goal of all activities carried out by PE “Roads of Serbia” in the scope of its work.

 