Remedial works on the landslide at Nikšićko brdo, on the expressway Batočina – Kragujevac, are being carried out in accordance with the established work schedule and they are making progress as planned.
The first phase of the works saw the placement of 75 piles and the deposition of 15 thousand cubic metres of stone material into the body of the embankment, while in the second phase of the works, another 57 piles have been predicted for installation.
The works are being carried out under traffic and they are provided with adequate traffic signage and equipment.
You may watch the statements of Vladimir Radosavljević, Head of the Department for Landslides within the Sector for Maintenance of I and II Category State Roads at the PE “Roads of Serbia” and Milan Slović, the representative of the Contractor, the Road Company “Kragujevac”, regarding the on-going works on this road, as well as the video footage recorded on the construction site, on the following link: Sanacija klizišta na putu Kragujevac-Batočina